The Code of Practice on the Conduct of Adjudications has been published in accordance with section 9 of the Construction Contracts Act, 2013 by the Minister of State for Employment and Small Business, Mr Pat Breen TD.The Code of Practice is binding on all adjudicators operating under the Act regardless of whether the Adjudicator is appointed to a payment dispute under section 6(3) or 6(4) of the Act.
0 Comments
The introduction of the Construction Contracts Act 2013, which commences for all Construction Contracts entered into after the 25th July 2016, has for the first time, removed the ability for a party to a Construction Contract, to make a payment conditional on the making of a payment by a third party.
Section 3 (5) of the Act, has been introduced to remove this element from Construction Contracts. Long the bane of sub-contractors, the pay when paid clause of many current Contracts, has effectively resulted in sub-contractors acting as part financiers of projects long after their works are completed. Coupled with the inability of parties to contract out of the provisions of the Construction Contracts Act, under section 2(5), these charges will mark a significant shift in the movement of cash-flow in Construction Projects. The Act, under section 4 (3) also for the first time places a requirement on the paying party, who disagrees with an amount claimed in a payment claim notice, to provide a response not later than 21 days after the payment claim date specifying, the amount they propose to pay, the reason for the difference and the method of calculation of their proposed value. This differs greatly from the current Contract provisions where, like the RIAI articles of agreement 2012 edition, under section 35, an explanation for any difference must be requested. In addition the inclusion of clause 4 (3b), means that even where an agreement has not been reached in respect to the difference between the parties, the amount that the paying party has agreed to in their payment response, must be paid by the payment due date. This again goes to the heart of the purpose of the Construction Contracts Act, which was to facilitate the positive flow of cash in a project. Section 4(4) of the Act, is an attempt to formalise the issue of contra charges, which are regularly a form of contention in the current final account process. This section allows for the paying party to formally identify contra charges for breach of contractual or other obligations within a contract and to make adjustment for same from a payment claim notice. They place a requirement on the paying party to detail the contra charge in terms of when and how the claim arose, the particulars of the loss, damage or claim and the apportionment of any claim. The wording of the Act, has however, not placed an obligation on the timing of the contra charge adjustment, and it is therefore likely, and unfortunate, that the issue of contra charges arriving late in the final account process is still very much alive. Keith Kelliher is an Accredited Adjudicator, who has completed the Diploma in Adjudication in University College Dublin, specifically on the Construction Contracts Act 2013, and has represented Main Contractors and Sub-Contractors in payment disputes for over 15 years in the Irish construction industry. Contact Keith at [email protected] for any assistance with the requirements of the ACT. The introduction of the Construction Contracts Act 2013, which commences for all Construction Contracts entered into after the 25th July 2016, has for the first time, introduced under statute a right to suspend work for non-payment. Section 5 (1) of the Act allows a party to a Construction Contract, to suspend work if they have not received payment in full by the day in which the amount is due.
The interesting inclusion to the section is the words, in full. There is therefore a clear statutory requirement on a party to a Construction Contract to make payment in full as opposed to the current trend to make interim payments on account. This introduces an interesting reality to the manner in which payments in Construction Contracts are to be certified in future. In order to suspend work, notice must be issued in writing to the other party to the Contract and it must specify the grounds on which it is intended to suspend work. It must be delivered between the day after the day the payment was due and at least 7 days before the suspension is due to begin. In order to cease a suspension, a party can make payment of the amount due or interestingly the suspension must stop if a decision is made to refer a dispute to Adjudication. In order to protect the contractor seeking payment, a justified suspension cannot be used against the contractor in respect to programme delay and disruption calculations. Contractors must however be careful in respect to suspensions, as an unjustified suspension will not protect a Contractor from claims in respect to loss and expenses as a result of delay to programme. Contractors must refer to the payment claim date schedule of the contract (or the Schedule to the Act should same apply), in order to confirm the day in which the amount is due. By way of example if the Schedule to the Act was the basis of payment claim date under the Contract the following would apply. Project Commencement Date Day 0 Payment Claim 1 Date Day 30 Latest Date for issuing a Payment Claim Notice (Valuation in old terminology) Day 35 Latest Date for issuing a Payment Claim response Day 51 Payment Due Date Day 60 Earliest Date that works can be suspended (subject to correct notification) Day 68 Keith Kelliher is an Accredited Adjudicator, who has completed the Diploma in Adjudication in University College Dublin, specifically on the Construction Contracts Act 2013, and has represented Main Contractors and Sub-Contractors in payment disputes for over 15 years in the Irish construction industry. Contact Keith at [email protected] for any assistance with the requirements of the ACT. The Construction Contracts Act 2013, will come into force for all Construction Contracts entered into after the 25th July 2016. With its introduction comes a plethora of new terminology for the industry to both understand but now to also religiously stick to. We say goodbye to the term valuation which has been replaced with the term “Payment Claim Notice” and a new term of a “Payment Claim Date” has been introduced. So what do they mean?
Payment Claim Date The payment claim date is the date when a payment claim is required to be made. This date must be agreed at the time of commencement of the contract or at least a mechanism for calculating same otherwise the Schedule of the Construction Contracts Act will apply. When it comes to subcontracts the Schedule applies in all instances unless the terms agreed are more favourable to the subcontractor. The schedule states that the payment claim date is 30 days after the commencement date in the contract and every 30 days thereafter up to the date of substantial completion and then 30 days after the date of final completion. Why is this date important? Well in accordance with section 4 of the Act, in order to receive the protection (based on the current untested wording of the ACT) of the ACT, a contractor has 5 days from the Payment Claim Date with which to issue a Payment Claim Notice. The schedule to the Act also states that no payment due under a Construction Contract can be made later than 30 days from the Payment Claim Date. It will therefore be, for contractors and subcontractors to regimentally submit their payment claims within a tight period of time into the future as opposed to the generally loose and haphazard methods that valuations are currently submitted, whilst also providing a tighter window for the receiving party to the Contract to deal with and certify the payment. Payment Claim Notice The introduction of a Payment Claim Notice in the Act must be seen as an apparent attempt to formalise and standardise a payment request process in the Irish Construction industry. For those currently working in the area of payment certification, the attempt to standardise the information that must be submitted will generally be welcomed. A Payment Claim Notice is a notice which specifies:
Time will tell how the industry reacts to the new requirements and obligations. Keith Kelliher is an Accredited Adjudicator, who has completed the diploma in Adjudication in University College Dublin, specifically on the Construction Contracts Act 2013, and has represented Main Contractors and Sub-Contractors in payment disputes for over 15 years in the Irish construction industry. Contact Keith at [email protected] for any assistance with the requirements of the ACT. Minister Nash Signs Order Implementing the Construction Contracts Act, 201313th April 2016
The Minister for Business and Employment, Ged Nash, has today signed the 'Construction Contracts Act 2013 (Appointed Day) Order 2016' which will give legal effect to the provisions of the Construction Contracts Act, 2013. The Order states that the '25th July, 2016 is appointed pursuant to section 12(2) of the Construction Contracts Act 2013 (No. 34 of 2013) and that Act shall apply in relation to construction contracts entered into after that date.' Minister Nash said: “This is a significant day in the calendar of events leading to the implementation of this important legislation and I am very pleased to be in a position to make this Order. It will transform the landscape in which the construction sector operates in Ireland.” The Minister added: “The changes to the way applicable construction contracts will now be drawn up will guarantee payment to sub-contractors at regular intervals during the life of a contract, and in addition, the legislation provides for a statutory adjudication service which entitles parties involved in a payment dispute to seek to resolve the matter through adjudication. This will take place in a short time period – the Act envisages 28 days.” It is intended that the Code of Practice relating to the conduct of adjudications will be published in coming weeks. ENDS For more information contact Press Office 01 631 2200 or [email protected] Keith Kelliher has been nominated as a panel mediator, by the CIArb Irish Branch as one of the participating Nominating Bodies for the Chambers Ireland Business and Commercial Mediation Pilot Scheme.
Minister Nash announces his intention to appoint Dr. Nael G. Bunni as Chairperson of the Panel of Adjudicators under the Construction Contracts Act, 2013
The Minister for Business and Employment, Ged Nash TD, has today (Tues 12th May) announced his intention to appoint Dr. Nael G. Bunni as Chairperson of the Ministerial Panel of Adjudicators to be appointed under the Construction Contracts Act, 2013. Dr. Bunni has extensive knowledge and wide ranging experience of dispute resolution in the Construction Industry both in Ireland and internationally. Minister Nash said: “I am very pleased that Dr. Bunni has agreed to accept the role of Chairperson of the Panel of Adjudicators. He has a proven track record of dispute resolution at the highest level in the Construction Industry and he has the right skills and the essential knowledge to chair the panel of adjudicators that I will appoint following an open competitive process to be run by the Public Appointments Service, which will commence at the earliest opportunity following his appointment.” Dr. Bunni said: “I would like to thank Minister Nash for selecting me to be the Chairperson of the Panel of Adjudicators and I look forward to working with Minister Nash to implement the Construction Contracts Act, 2013 for the benefit of all stakeholders in the Construction Industry.” The Government approved the delegation of responsibility for implementation of the Construction Contracts Act, 2013 to the Minister for Business and Employment last November and work is continuing on the preparations for the full implementation of the Act as soon as possible. The Construction Contracts Act, 2013 provides, subject to some exceptions, new minimum contractual provisions concerning payment arrangements between the parties to a construction contract. Where payment disputes do arise between the parties to a construction contract, either party will have the right to refer the payment dispute to adjudication, which will be concluded within a set timeframe. Where the parties cannot agree on an adjudicator, the Chairperson of the Ministerial Panel of Adjudicators will appoint an adjudicator from the Panel to the dispute. - See more at: http://www.enterprise.gov.ie/en/News/20150512.html#sthash.m2v8v17Y.dpuf Please click on the link below to see our You Tube video on adjudication and the Contraction Contracts Act 2013 brief introduction to adjudication |
AuthorKelliher & Associates experts in the field of Dispute Resolution and provide this information for education and reference in the field. Archives